In terms of innovation and infrastructure, the project has an area of 43,500 square meters (which is more than 5 times the area of the Doroteo Guamuch Flores National Stadium), a capacity of over 12,000 pallets (6 times the current storage capacity), 29 dispatch doors, and a product selection system via automated voice command
Attached to customer demand, a large complex was built that guarantees the productivity and efficiency of operations, composed of full web structures, lattice structures, and large-scale spatial structures.
The project was developed with the advice of the Guatemala Green Building Council, a sustainable building council that seeks to promote best design practices in the country.
This distribution center will generate 22 percent of its energy through solar panels, and the remainder through other renewable energy sources. Additionally, it features waste management, a water treatment plant, and a 45 percent water efficiency system. The foregoing translates into 46 percent energy efficiency, with which this new PepsiCo facility will be applying for LEED certification.
Land Area 430,000 m²
Cut 157,000 cubic meters
Stuffing 75,000 cubic meter
Retaining Walls 2,700 square meter
Maneuvering Areas 14,500 square meter
Parking lots 1,500 square meter
Patio Concrete 3,200 cubic meter
Corner store 12,800 square meter
Height 17 meters
Total width 63 meters
Total length 203 m
Loading and unloading bays 29 Units
Foundation depth 12 months
Concrete floor 2,600 cubic meter
Super Foundation Plan 810 cubic meter
Administrative Building 1,916 square meter
Capacity 300 Personas
Runtime 12 Months
Hired people 250 Personas
Earthquake CAT 4
Hurricane CAT 3